ELECTRIC CONNECTION : TECHNICAL FEASIBILITY FOR MAJOR LOADS

1.

Acknowledgement application.

Within 7 days.

2.

Scrutiny of application.

15 days.

3.

Information to applicant about deficiencies.

15 days from date of application.

4.

Issue of NOC if sub-station is not required.

21 days after completion of formalities.

5.

Approval of space for substation on submission
of deposit of approval fees.

Within 30 days of submission of drawings and technical details.

6.

Estimate for establishing Electric Substation.

a) Within one month for deposit work.
b) Within 3 months if there is municipal contribution.

7.

Deposit of estimated amount by applicant.

Within 30 days after issue of sanctioned estimate.

8.

Execution of work.

With 6 to 9 months after deposit and availability of built up space for substation in working condition.

9.

Sanction of load.

Within 30 days after receiving completion report from EE (Construction).